British Embassy
2026
A turnkey groundwater source
Addis Ababa
A complete groundwater source: survey, a 250 m well, and a submersible pump connected to the tank.
- Well depth
- 250m
Survey · Drilling · Pump and tank connection
View project
Project · Ethiopian Airlines
Drilling and construction of two 500 m wells, with a pumping test confirming a yield of 40 litres per second.
In 2024 we drilled, tested and equipped two 500 m wells in the Ethiopian Airlines compound in Addis Ababa, working on behalf of Kibish Construction, the main contractor.
It was a job for the whole life of a well, not only the drilling. Each well was taken from the first metre of the borehole to a tested water supply with its pump installed, and the wells were proven before anyone designed the system around them.
Our drilling, pumping-test and installation teams worked through four stages:
Our pumping-test crew brings its own submersible pumps, crane and generators to site, which is why one contractor could drill the wells and prove them.
The pumping test confirmed a yield of 40 litres per second.
That figure matters because the pumps and the pipework are chosen from it. The test verified the capacity of the wells and gave the performance data for selecting the pumps and designing the distribution system, so the design starts from measured performance, not from an estimate.
Two tested wells, finished in 2024, for the national airline.

British Embassy
2026
Addis Ababa
A complete groundwater source: survey, a 250 m well, and a submersible pump connected to the tank.
Survey · Drilling · Pump and tank connection
View project
Palace Administration / Etoile GC PLC
2022
Addis Ababa
A 600 m well — the deepest on our completed list — for the Chaka House development.
Drilling · Well construction
View projectTell us where your site is and what you need. We reply with a clear next step.